456 prefab bathrooms

Yours phase 2

Leiden

Project details
ClientSchouten Techniek
InvestorSyntrus Achmea Real Estate & Finance
DeveloperVOF De Leidse Schans (VORM Ontwikkeling en Ballast Nedam Development)
ArchitectMecanoo
Contractor(s)Ballast Nedam Bouw & Ontwikkeling, Schouten Techniek, Ursem Modulaire Bouwsystemen
LocationLeiden
Building systemPrefabricated bathrooms
Type of buildingApartment building
Number of Modules456
Production rate4 per day
Year2018-2019
This project has been finished See the project page for more information.
Go to project
2019

Today, phase two of student campus (Y)OURS has been festively opened by Minister Kajsa Ollongren. On behalf of partner Schouten Techniek BV we supplied 456 prefab bathrooms.

From week 11, the 211 apartments of Block F, in which our bathroom modules are incorporated, will be completed.

This is expected to take four weeks and we hope, of course, but we also have faith in smooth delivery.

2018

Today the last 3, out of a series of 456, prefabricated bathrooms for project Yours phase 2 in Leiden have been delivered.

2017

Start of construction phase 2 De Leidse Schans (Yours), Leiden